Similar to the first phase of the Heavy Equipment Transport process, the 185-ton cargo was barge-transported by the tugboat up to the temporary jetty erected at the outfall of the Hamilton Canal. The equipment was then land transported via a multi-axle low bed trailer from the jetty location to the site, via the Hendala-Hunupitiya road.
Simultaneously, the smaller capacity transformers comprising of the Unit Auxiliary transformers, Black Start Generator transformers and station transformers reached the project storage from the Port of Colombo via another guided road transportation process.